Critical path installation order — acoustic isolation depends on correct sequencing. Every phase must be completed in order. Skipping or reordering steps will compromise the acoustic envelope.
CUSTOMIZABLE -- Scaffolding and temporary works supplier, site safety signage style, worker scheduling and shift patterns, tool brands, dust protection and site cleaning methods, delivery logistics and staging areas, progress reporting format.
DO NOT ALTER -- Phase sequence order (slab & float floor with floor box stub-ups before walls, electrical rough-in during perimeter wall construction while cavities are open, buffer spine before internal partitions, door frames before HVAC rough-in, HVAC and above-ceiling cables before ceiling systems, door hanging after ceiling systems, finishes & fixtures last before testing), hold-point inspection requirements, curing times between phases, seal-before-close protocol, STC verification testing at each stage. Changing the build order compromises acoustic isolation. Follow the sequence exactly as specified.
Visual timeline showing all phases with estimated durations. Total estimated: 6–8 weeks.
Complete each phase in order. Check off tasks as they are completed. Progress is saved automatically.
400mm centers)
18mm T&G, screw to pads only)
200mm)
10mm maintained all around — DO NOT seal yet (seal AFTER walls complete)
x=100, y=76) and ST-FB (Video Studio, x=671, y=310)
3mm deviation over 2m)
400mm OC verified
3mm gap), seal perimeter with acoustical sealant
≥300mm
X=206–221, STC-55 target)
32mm steel EMT
80×50cm, VO/Control partition, STC-53 target)
32mm steel EMT
25mm EMT, 600mm separation from power) to all Cat6A outlet locations within partitions
10mm gap + seal
20mm for D1 (Entry) / 18mm for D2–D4
300mm minimum straight duct upstream AND downstream of every silencer — elbows or transitions at the silencer face reduce attenuation by 3–8 dB
1m flex)
600mm audio-to-power separation maintained
600mm minimum between power and audio cables. Data cables: 300mm from power. 90° crossings only where paths must intersect
2.75m AFF — verify level
10mm gap all around)
85mm total thickness)
These sequencing rules are non-negotiable. Violating any of them compromises the acoustic isolation envelope.
600mm minimum parallel separation. Power and data cables 300mm minimum. Crossings at 90° only. Analog audio NEVER shares conduit with digital (ethernet, DMX) or AC power.
Overlapping phases shown with dependencies. Critical path highlighted.
After each phase, perform these verification steps before proceeding.